Logwood Place

Housing Context

Across the country and here in Wigan borough there is unprecedented and growing demand for affordable housing. Wigan Council’s Housing Register has more than doubled over the last few years to about 15,000 applicants.

Through our new build housing programme, we are working proactively to deliver sustainable, affordable homes, in line with current and future housing legislation, and the need to play our part in tackling climate change.

 Logwood Place

The council actively manages its land and property to ensure that it is used to best effect to meet local priorities; including delivering much-needed good quality, affordable homes and Logwood Place has been identified as a potential site.

 Proposals

Alternative options, including the cost and ability to refurbish and bring the homes to future requirements has been assessed. The proposal is to redevelop the site for an apartment based scheme owned by the Council for rent (including a number that are fully adapted for wheelchair users) designed to high space, energy efficient and sustainable standards to meet a range of needs and aspirations.

The total number of homes and what the scheme may look like, should the proposals proceed is to be determined through tenant and resident engagement and subject to Planning consideration. This progress is shown in the phases below.

You're viewing real-time data. Participant counts are continuously updated for administrators. Please note that regular users see cached data, which may result in slight differences in the numbers.
2 participants

Open for participation

Phases

Phases overview
Logwood Place Consultation
Logwood Place Pre Planning Consultation
Logwood Place Planning Phase
Logwood Place Demolition
Logwood Place Update

Logwood Place Update

18 February 2025 - No end date

Redevelopment Update

Further to our last update in 2024, informing you of the demolition of the two blocks at Logwood Place, we would like to update on progress regarding the redevelopment of Logwood Place.

The area has seen the erection of site security hoarding around the site which is to remain for public safety.

Further site investigation surveys were required following the demolition of the existing blocks and we have been awaiting costs for the diversion of utility services, which were required prior to starting construction. This took longer than anticipated to complete.

We expect the diversion works and the site investigation works to commence in the spring, taking approx. 3-4 weeks to complete which will allow construction work to start.

We will update again in the spring before the site works are due to commence with further details on the timescale.

For any other comments or questions, please contact the New Homes and Regeneration team by commenting on this site or via e-mail at NewDevelopment@wigan.gov.uk

0 issues

No results found. Please try a different filter or search term.

Filters

Total posts: 0
There are no projects available.

Sorting changed to: New

No values available.

Selected zero tag filters.

Upcoming and ongoing events

    0 events have loaded.
    No upcoming or ongoing events are currently scheduled.

    Past events

    3 events have loaded.