Next Steps

Be Informed and Get Involved!


Learn more about what happens next; from getting involved with our consultation events, to what happens after the consultation closes.

You're viewing real-time data. Participant counts are continuously updated for administrators. Please note that regular users see cached data, which may result in slight differences in the numbers.
2 participants

Phases

Phases overview

Developing Designs

1 July 2022 23:00 - 1 January 2023 00:00

The preceding months were spent analysing all the feedback we received and developing the scheme designs.

  • A number of design iterations were presented to key stakeholders, including ward members, schools, blue light services, network management and Leigh Neighbours Project committee.
  • Traffic surveys were undertaken to understand the movement of all traffic coming in and out of the area.
  • The scheme designs were presented to Transport for Greater Manchester's (TfGM) design review panel to ensure they met LTN 1/20 design guidelines.